Blog

  • Progress on Net Zero Home in Fairfax

    Weather has been a killer, but we are finally out of the ground, and framing lumber is onsite and ready to go up. This spring has had the longest stretch of rainy days since the 1880’s, which has been great for my garden and our trees, but not so good for excavation and the pouring of concrete. Here are photos of progress to date..

    DSCF4709 The site, cleared and with excavation equipment ready.

    DSCF4712 Excavation work in progress.

     

    DSCF4918  A dry day with footings in place. On this project we used our standard high density eps foam footings over a mudslab. At sides and top of footings, however, we used 2 layers of 2″ Roxul Comfortbat CIS mineral wool.

    DSCF4922 Note the waviness of the sides of the footings. We used rebar set into the ground to hold the side insulation in place to work as our formwork. Whereas a foam would have withstood the pressure, the mineral wool, less stiff, gave way to the pressure.

    DSCF4920 It was also difficult to keep the mineral wool in place after pouring, as this picture shows.

    DSCF4935 Here you can see the high density EPS sitting on the mudslab. We ran it out 4″ past the edge of the concrete to provide a base for the mineral wool at the sides.

    DSCF4939 April 5th. Formwork now in place.

    DSCF4950

    DSCF4952 Note the haunches that will carry the slab under the front entry stone.

    IMG_5786 April 18. Formwork is down. Ready for waterproofing.

    DSCF4982 Footings may be wavy, but the walls are true!

    DSCF4963 The mineral wool did not stand up well to the setting up and taking down of forms. Much was knocked loose and abraded. We had to come back later and replace some, and fill gaps with canned foam. This is an example of the damage.

    IMG_6690Foam enclosure around sump crock.  Where before we had a circular piece of foam made up to wrap the crock, we found it easier to make a simple box and then fill in with gravel behind after setting crock.

    IMG_6678 A mountain of 4″ EPS foam waiting to go under the slab. Our intention was to use Roxul Comfortbats, which have a much lower global warming potential (GWP). While it has been widely used under slabs in Canada and Europe, because Roxul has not produced an ICC report for that application the city wouldn’t allow it. We resorted to the foam we have used on our past PH projects.

    DSCF5037 May 5. Carlisle MiraSeal waterproofing in place. This is amazing stuff. Great bonding to the concrete, tough and flexible.

    DSCF5029 A wall penetration. No need for any further sealing after using the MiraSeal!

    DSCF5024 The entire underground insulation and wall drainage system is being installed by Aird, Inc. The also did the Sto EIFS system on our Rockville passive house. Rob Aird has been a great partner in the planning and construction of these houses. Here the Aird crew is installing the second 2″ layer of the Comfortbats. Note the staggering of the joints to prevent air gaps that would reduce thermal performance. Notice  also all the cans of glue and adhesives lying on the ground. This stuff is hard to hold in place and doesn’t adhere well to much of anything. In the end they used Liquid Nails to adhere to the Carlisle MiraSeal and Carlisle Hardcast Travel Tack spray adhesive to adhere the two layers of insulation.

    DSCF5026 The southeast corner, with mineral wool application in progress.

    DSCF4992 Izumi, David and Matt on a site visit.

     

     

  • Passive House Gaining Interest in the DC Area

    On April 12 Matt and David were asked to do an all-day presentation on passive house design principles for Halfmoon Education Inc., a continuing education organization that sponsors programs for architects and engineers. Around  twenty architects and several engineers  and developers gave up their day to attend, which to us is a very good sign of the growing interest in high performance homes.  From the feedback we got, their main motivations in attending were client interest and their own desire to build higher performing homes using an integrated approach to design. There were lots of good questions and some good discussions.

  • Groundbreaking this week on the first Net Zero house in Fairfax City

    Front elevation-cropped

    The bulldozers are on the site, and barring rain, they will begin excavation on Fairfax City’s first net zero home. The house was designed using Passive House principles, and the owner is anticipating that the 20 kw solar array planned for the garage and main roofs will power both the cars and the home. We will be blogging about the project as it moves forward.

  • Matt and David spoke at recent events

    NESEA Conference
    On March 9th Matt presented the Weinberg Commons Passive House Retrofit in a presentation called  Passive House Deep Energy Retrofits: Revitalizing Masonry Multifamily and Single Family Wood Frame Buildings.  Matt was the project architect for this retrofit — the first passive house retrofit in the DC area —  with his former firm of Zavos Architecture + Design. Here is a link to his talk. Go to minute 39 of the talk.

    AEE National Capitol Area Conference
    On March 25 David participated in the panel discussion: Passive House, Living Building and Related Ultra-Low Energy Standards, held by the Association of Energy Engineers National Capitol Area Chapter.

    Halfmoon Continuing Education Seminar
    On April 12, Matt and David led an all day seminar sponsored by Halfmoon Education Inc., entitled Passive House: Planning and Design, in Fairfax, Virginia.

     

  • Matt Fine, CPHC®, LEED AP® joins our firm

    We have exciting news. On January 4, Matt Fine will join the firm and bring with him over 10 years of experience in affordable multifamily housing work.  Since his 2010 PHIUS training, Matt has done pioneering work in high performance multifamily housing as Director of ZA+Dpassiv, a division of Zavos Architecture+Design, LLC (ZA+D).  He was the project leader of that firm’s very successful Weinberg Commons (projected PHIUS+ certification 2016), a  retrofit of 36 affordable dwelling units within three 1960’s era buildings.
    As a Certified Passive House Consultant, Matt has also led high-performance single family home projects.  He collaborated on the 2011 Arlington Passivhaus, actively consulted with Parsons The New School for Design on the 2011 Solar Decathlon entry known as Empowerhouse (PHIUS Certified), and captained the Ivy City Passive Townhouse project through its duration (projected PHIUS+ Certification 2016).
    We are delighted to have him join our team!
    Matt’s new email address is matt@greenhaus.org.

    Matt Fine, Peabody Architects

  • Modular Passive House is now completed

     

    The HIP modular Passive House is now completed, with all systems installed. HIP held a grand opening in late November, attended by Patricia Waiters, Mayor of Fairmount Heights, and officials from the Prince George’s County Department of Housing and Community Development and the Maryland Department of Housing and Community Development. The Prince George’s County DCHD and Maryland DCHD both helped in funding the project. A Voice of America crew was their to do interviews, and that can be seen at this site: http://www.voanews.com/content/airtight-houses-lower-energy-costs/3086684.html.

    Final steps remaining before Passive House Certification are the final blower door test and duct testing. These will be done in the next two weeks after the mechanical contractor has completed balancing the system. Here are some photos of the finished product…

    Modular passive house exterior
    South elevation

     

    Modular passive house exterior

    Gable detail

    Modular passive house exterior
    View from south west

     

    Modular passive house interior
    Kitchen, looking toward front door

     

    Modular passive house interior

    Kitchen looking toward dining and rear door

     

    Modular passive house interior
    Living area looking toward kitchen

     

    Modular passive house interior
    View from the stair
  • Second modular Passive House blower door test results!

    Chris Conway and crew were able to get back at the site on September 3rd for a second test, after taping of the various leaks we’d uncovered  on August 26th. The big culprits, we believe, were the gaps at each of the straps between the top and bottom modules.

    The results: .40 ACH50Pa.  Our tightest house yet!

    Here are a couple of before and after taping shots:

    first blower door test 04straps before

    20150827_150111_resized straps after

    first blower door test 01 damaged floor tape

    20150827_134353_resizedre-taped floor

     

  • First modular Passive House blower door test results

    Chris Conway and Caleb Fritsch of Conway Energy performed the long-awaited blower door test for our first modular passive house today. We couldn’t have picked a more beautiful — and simultaneously more inopportune — day to have scheduled it. Good forensic testing requires a greater than ten degree difference between inside and outside temperatures so that a thermal imaging camera can “see” the temperature differences where air is leaking. For example, when the interior of the house is cooler than the outside air, leaks coming in will read as orange or red plumes against a blue background during a depressurization test. Conversely, in a pressurization test leaks from within will show up against the outside of the house as blue plumes against an orange background.

    Trouble was, on this August day the high was a balmy 78 degrees and we had only been able to get the interior temperature down to 72 degrees with the single window unit we had hooked up to the generator! (The main cooling system could not be run since the house is not yet connected to the grid.)

    So the ever-resourceful Chris pulled out his smoke pencils, which were better than nothing. With them you can spot leaks by the change in direction of the smoke as you pass it over a leak. But it is far far more tedious and less efficient that using thermal imaging. We were able to use the camera in the attic space, however, which was well over 90.

    It was a nervous moment when Caleb started the fan. The result: .65 ACH50Pa (air changes per hour at 50 pascal of pressure) on our first try. We were delighted with that number, having had no idea what to expect. Chris found enough leaks with his smoke pencil that, in his view, we should easily get below the required .60 ACH50Pa by fixing them.

    Most of the leaks were beginners’ mistakes, which we will chalk up to lessons-learned. All are easy to fix:

    • The taping of the joints at the first floor subfloor had been damaged by foot traffic in a number of places in the course of the construction. We will re-tape those joints , and in the future we will make sure the subfloor tape is covered by a protective layer during construction.
    • The men taping the joint between the top and bottom module had run the tape over the metal straps that connect the two modules, thereby leaving a crack every two feet or so where the tape was discontinuous. This led to a number of leaks around perimeter at that line. It is an easy fix, and avoidable in the future by taping before the straps are bent into place.
    • While factory penetrations were all sealed by rubber gaskets and tape, the penetrations made in the subfloor after the house was set were only sealed with foam. Vince will cut the foam back and seal around each of this penetrations with a sealant gun, and tape where appropriate.
    • We forgot to tape the overflow holes at bathroom vanity sinks. Right now these are holes to the exterior since the plumbing is not yet hooked up to the sanitary sewer line to the street.
    • The attic hatch doorway, provided by Conservation Technologies, was remarkably airtight. It leaked, however, around the rough opening in the framing where in which it was installed. They had used foam to seal that gap rather than air seal tape. Again we will remove enough of the foam to allow a continuous band of tape around the frame.

    John Meredith and his crew at Beracah Homes should feel very proud to have achieved this test result on the first try of their very first Passive House.  It represents a very meticulous assembly process. To put it in perspective, the leakage recorded today is the equivalent of roughly a 3″ diameter hole in the entire building envelope. Chris reckons that by reducing that figurative hole by 1/4″ we will achieve the .60ACH Passive House standard.

    Here are a few pictures from the day…

    first blower door test 01   finding leaks with the smoke pencil in torn first floor taping

    first blower door test 04the interruption in the taping between the top and bottom modules — no need for a thermal imaging camera to see these gaps!

    first blower door test 03the view from the inside of the gaps shown above — note the steady directional stream of smoke.

    first blower door test 02foamed site-made penetrations at the first floor — the foam will be cut away flush with the floor surface and sealant will be applied around each opening. Same drill will be performed at the bottom surface penetration.

    IR_0837This infrared photo shows the attic floor. Angled lines in the background are the rafters. Those in the foreground are the framing for the midspan rafter support. When we saw that big patch of blue we figured there was a lot of air somehow escaping from the house into the attic. A closer look revealed that the area was still damp from where the solar panel folks must have spilled some water during installation of the panels. The blue is caused by evaporative cooling!

    IR_0838Looking down at the attic floor and the folded up attic stair. The blue shows leaks between the attic framing and the frame of the attic stair unit. This was foamed not taped, and this shows why we prefer tapes.

  • Our modular Passive House is on its foundation

    Second floor ext wall corner-29

    Architects rarely see sudden transformations. Our work is composed of small incremental steps, generally forward, from fuzzy concept to finished building. The pace usually seems glacial and there is never, ever, a big WOW moment when what we do suddenly becomes a building. So it was a unique experience today watching our first modular house go up. To see a site go from empty foundation in the morning to fully erected and enclosed house in the afternoon — that was indeed a first for us!

    Things began quickly. They had brought the modules over from Delaware on Monday and parked them in a nearby parking lot, so they were at the site by 8. The first floor was a bare box. The second floor box had the folded up roof on top of it. By 9:30 the first floor module was already on its foundation.

    The second floor module took more time, as the set crew decided to completely erect the roof while the unit was still on the ground and more easily accessible. Also safer to fall from 9’ rather than 19’ if there were an accident. So the rest of the morning and early afternoon went into the process of unfolding the sections, attaching the eaves, then tilting the roof up into position. It was a beehive of activity with a crew of about 15 men and boys all busy all the time. Around three, things got very quiet, the hammering stopped, and all the workmen stepped back to watch the crane operator do his magic. Lifting the second floor and roof into place took exactly six minutes. Voila, we had a house!
    Here are some of the high points in photos….

    last clean up of crawl space
    Last chance to clean up the crawl space

    8 am
    8 am. Waiting for a house.

    Second floor ext wall corner-16
    9:30 am. First floor on the foundation.Second floor ext wall corner-4

     

    Second floor ext wall corner-2                                              Perfect fit!

    Second floor ext wall corner-5
    The hold-down metal straps are embedded in the concrete and will now be fastened to the structure.  The factory-applied blue Tescon Vanna tape makes the seam between the sheathing and the rim joist airtight. Another piece of the Zipwall sheathing (the green stuff) will now be anchored to the wood sill plate below and the rim joist above to make the whole assembly monolithic.

    Second floor ext wall corner-3
    These metal straps will anchor the first floor module to the second floor module. The taped up box you see there is a junction box for one of the exterior awning motors.

    Second floor ext wall corner-7
    The cheering section: Brendan O’Neill with Jocelyn Harris and Maryann Dillon of HIP

    Second floor ext wall corner-8
    The second floor module now pulled into position. Note how the right side of the roof is of one piece but the left side is made up of two segments with an elbow. This is done so that they will lie as flat as possible for shipment down the road in order to stay under the maximum shipping height limits.

    Second floor ext wall corner-9
    Loading the eave overhangs onto the deck from the truck. They have to be added at the site; otherwise the width of the unit would exceed the maximum shipping width limits.

    Second floor ext wall corner-10
    Beginning to attach the eaves to the rafter ends.

    Second floor ext wall corner-6
    More of the same.

    Second floor ext wall corner-14
    Meanwhile Vince Coffin, our jobsite supervisor, adds some more Vanna tape as an extra sealing precaution.

    Second floor ext wall corner-15
    Eave overhangs now in place.

    Second floor ext wall corner-12
    Inside the first floor module Brendan O’Neill and Vince Coffin confer with John Meredith. John shepherded the house through the factory design and construction process from beginning to end.

    IMG_4318
    A couple of spectators in the stairway on top of the first floor module.

    Second floor ext wall corner-17
    Roofs with their eaves attached now tilted up into place.

    Second floor ext wall corner-22
    Inside the attic, the hinges that the rafters pivoted on.

    Second floor ext wall corner-19
    Kneewalls,…Second floor ext wall corner-18… gables, and rafter ties all on the truck waiting to go up.

    Second floor ext wall corner-23
    Kneewalls being delivered.

    Second floor ext wall corner-24
    Kneewalls now in place. Rafter ties being delivered, while above men are installing the ridge vent for the roof.

    Second floor ext wall corner-25
    Now the gable ends are set in place.

    Second floor ext wall corner-26Setting the cables in place….Second floor ext wall corner-28… and running them under the module.

    Second floor ext wall corner-27
    The metal strap is there to prevent any chafing by the cable during hoisting.

    Second floor ext wall corner-30
    3:30 pm. Top unit in place.

    Tomorrow the electrician, plumber and mechanical contractor arrive to make the hookups between first and second floor units, while carpenters finish attachments between the units and the the foundation. Then taping of the joints between modules and penetrations in preparation for the blower door test at the end of next week.

    I will add video of the actual setting of the units when available.

     

     

     

     

     

     

     

     

  • Preparing the site for our modular Passive House

    Sitework began in mid-July. Everything is now ready for the arrival of the modules on August 11.

    One of the ways we controlled costs on the project was to eliminate the conditioned crawl space, which on a passive house can be a very large expense, with the insulation of walls and footings just as is required in a passive house basement. As described in the previous blog, we opted to make the first floor framing the edge of our building envelope so everything below that is of standard construction.

    One issue we ran into in the design phase was the confict between the Building Science Corporation’s recommendations for an insulated floor first floor assembly over a crawl space, the building code’s requirements for crawl spaces, and passive house requirements. The issue is warm moist air in summertime getting into the floor assembly and condensing when in contact with the relatively cold floor structure.
    BSC would prefer we have a completely closed crawl space protected from below by a sturdy vapor barrier. This would keep moist summer air out of the crawl. They then recommend completely insulating and sealing the underside of the joists to remove any chance of condensation there. They also recommend monitoring the sealed crawl space for moisture and having a dehumidifier located there in case of any moisture build up.
    All fine, but the building code requires sealed crawl spaces to be ventilated with air from the interior of the house. That of course would completely erase all the airtightness we are struggling to achieve.
    What we decided to do was follow BSC recommendations completely, but to create a “ventilated crawl space” as defined by code, placing the minimum number of ventilation louvers in the exterior walls of the crawl space. Since we are allowed to make these louvers operable, we will simply keep them closed up, making the crawl effectively a sealed crawl space.

    Here are some pictures of the progress…

     

    The day work began
    The day work began
    Some of the brush we had to remove
    Some of the brush we had to remove
    Site cleared and ready for digging for footings
    Site cleared and ready for digging for footings
    Formwork in place
    Formwork in place
    Formwork in place - view from front
    Formwork in place – view from front

     

    Formwork in place - the south wall
    Formwork in place – the south wall
    Top plate and termite guard in place
    Top plate and termite guard in place; plumbing waste lines run, and ready for gravel fill
    Gravel fill in place
    Gravel fill in place
    Vapor barrier in place; waterproofing in place; backfill beginning
    Vapor barrier in place;
    waterproofing in place;
    backfill beginning
    passive house crawl space
    Vapor barrier in place, joints taped. The pile of insulation will be applied to the bottom surface of first floor joists after the house is set in place and joists cavities are filled with insulation.
    backfilling
    backfilling
    Crawl space vent open
    Crawl space vent open
    Crawl space vent closed
    Crawl space vent closed