Blog

  • Laying the Pre-tempering Ground Loop of PEX Tubing

    Posted from: MD, USA

    The exterior foundation walls have now been waterproofed and the insulation and drainage board installation is nearly complete. The steel for basement columns and beams is at the site, and we await the arrival of PanelWrights on Thursday to begin framing of basement walls and first floor framing. The first floor framing must be in place before final backfilling is completed so that there is resistance at the top of the foundation walls to the pressure of the earth.
    Yesterday Foley’s crew (Foley Mechanical, Inc.) was at the site to lay the PEX tubing for the pre-tempering ground loop. What is a pre-tempering ground loop? Basically we will temper the air coming into the household ventilation system with what you might call a “poor man’s” ground source heat pump. We are running a loop of about 300 feet of PEX around two sides of the building deep underground. Water will circulate through this tubing to a heat exchange coil in the ventilation air intake duct. The water, which will be at constant year-round temperature of 56 degrees Farenheit, will cool the incoming summer air and warm the incoming winter air. Foley will install monitors to measure the exact amount of btu’s that are transferred annually. A ground source heat pump operates according to the same principles as this, but runs refrigerants like freon through the underground lines and uses a compressor to “pump” the energy— considerably more complicated and expensive.

    We have integrated laying the tubing into the process of backfilling. The first step of backfilling involved putting down perforated footing drains in a gravel bed around the permiter of the house. Any water that gets down to that level will enter those drains and be taken away.

    Over that gravel is placed a geotextile fabric — basically a filter that keeps dirt from getting below to clog up the drains, but allows the free passage of water. It is the dark cloth at the bottom of the picture showing the exterior of one of the foundation walls. In this picture you can also see foundation insulation and drainage board, and above that the dark waterproofing.

    Over the geotextile fabric is about 8” of dirt, which is what you see at the bottom of the trench in the video. The men have laid down the first loop of PEX, keeping piping as far apart in the trench as possible. They are covering it with dirt by hand to hold it in place.

    Then a backhoe will dump 24” more of soil, compacted in 8” lifts (layers). The men will then repeat the process of laying another loop of PEX. The goal is to keep the individual tubes as far apart in the soil as possible so that the ambiant soil temperature will not be affected. If they were all laid in one big bunch of 4 tubes, the surrounding soil temperature would be changed, reducing the delta T for energy transfer. The top layer will be 5’ below grade.

    The PEX we used here is a Rehau product, proven in underground use in Europe over many years. Foley only has confidence in Wirsbo and Rehau as makers of this tubing. It is completely inert and will not deteriorate over time.

  • Katrin Klingenberg Visits the Site

    Posted from: MD, USA

    We have accomplished a lot since our last post.

    First, we laid a 6” gravel bed down over the soil. This provides a capillary break between the concrete and the soil, preventing the slab (basically a big sponge) from sucking up moisture from the soil below. Standard good construction practice.

    After the gravel was tamped level and compact, we placed 4” of EPS Geofoam over it. The EPS boards were laid tight together, with no gaps. One of the photos is taken just as the vapor barrier was about to be laid. You can see the foam is held back to allow the concrete slab turn down and rest directly on the concrete footing at its perimeter. Another picture shows the basement grinder pump set in its insulation bed. Mid Atlantic Foam took the crock and the radon crock to their shop and fabricated foam cradles for them. Bartley Concrete then simply made a depression in the gravel, and set set the cradles with their tops flush with the top of the rest of the foam, and dropped in the equipment.

    While the foam was being put down Bartley was also applying the waterproofing membrane to the exterior of the sub-grade foundation wall. In one of the photos you can see the membrane going down to the top of the footing. The temporary foam form has not yet been removed. When it is, they will apply the waterproofing with a roller all the way down the sides of the footings as well. Friday the 3rd was a big day. After all the sub-slab foam was in place, Bartley installed and taped the vapor barrier. We also had a surprise visit from Katrin Klingenberg, Director of the Passive House Institute U.S!

    The pictures show the 15 mil Stego polyethelene vapor barrier (http://www.stegoindustries.com/technical_info/_stego_wrap_15-mil_vapor_barrier.html) all laid out and taped up. We chose the StegoWrap over the standard 6 mil barriers because you have to really want to cut it or tear it in order to do so. Draping it down under the footings and up the wall, we wanted to be sure nothing inadvertently punched holes in it. All joints were taped continuously, and as you can see in the photos, all penetrations were fully double-taped as well. We temporarily tacked the edges up along the foundation walls until the slab is poured. Bartley will then come back and anchor a continuous metal termination bar along the top, mechanically fastening the barrier to the concrete. Katrin was in DC doing a training course for Passive House consultants. (http://www.passivehouse.us/passiveHouse/PHIUSConsultantsTraining.html) Of all days Katrin could have come, this was the best. It was a first for all of us at taking these extra steps of sealing, and having her go over our work and pronounce it first rate before the concrete went in gave us all a big boost.

    On Monday, after Keith made a final check of all the taping, the concrete trucks rolled up and poured the floor slab. I dropped by the site today and include a picture of the finished slap, with only the top of the vapor barrier peeking out. Another picture shows the same penetrations we photographed earlier, now encased in concrete and sealed tight. The group in the picture, left to right:
    Keith, Katrin, Brendan Jr., and Terry Hill, another Passive House consultant.

  • Foundation walls now in place.

    Posted from: MD, USA

    Foundation walls are now up, and the construction forms are off. Next
    steps will be waterproofing the exterior of the walls, then applying
    the underground insulation and drainage board. Tammy Fuller from
    Mid-Atlantic Foams was at the site measuring for insulation quantities
    when I visited and left us a sample of the insulating drain board (see
    photo below).

    This two inch thick board is designed to provide a “drainage plane”
    for the wall, creating a capillary break and channeling any water that
    gets to the wall down the face of the wall and into drains placed at
    the footings. It is composed of small foam balls which allow the
    passage of water. It is coated at its outside face with a layer of
    fine mesh (“geotextile”) which allows the passage of water but keeps
    dirt out. In our case this 2” board will be laminated to a another 2”
    thickness of expanded polystyrene insulating board designed for
    underground application.

    Creating a drainage plane in this way is not particular to Passive House construction; it is simply standard good construction.

    Pictures below:

    The walls from above and from inside basement.
    The insulating drainage board.
    Brendan O’Neill, Jr., Tammy Fuller, and Keith Kauffman

  • Foundation walls going up

    Posted from: MD, USA

    Yesterday we erected all the exterior wall forms, and today we will
    pour the foundation walls.

    Air sealing is critical in Passive Houses. To prevent any potential
    air leakage, we have minimized and clustered the number of
    penetrations through exterior walls. At our preconstruction meeting
    all subcontractors submitted exact locations of where they need to
    penetrate the building envelope, and worked together to consolidate
    those holes. We have placed sleeves in the formwork for all
    penetrations, which will later be sealed and insulated.

    Here are a few images:
    * a short clip of erection of the forms;
    * Keith Kauffman, Jobsite Superintendant, who is keeping it all on track;
    * rear frost wall footing with wall steel in place;
    * and a general view from the front yard. In the distance you can
    see the variety of houses in the neighborhood: two large new houses on
    the left and an older original house on the right. Our foursquare will
    be in the middle of that spectrum size-wise.

  • Passive House Footings Are Different

    Posted from: MD, USA

    To prevent thermal bridging (short circuits in the insulation system)
    the complete building envelope of a Passive House is insulated. In our
    case, this includes the footings. In this little film clip you can see
    that in progress.

    After excavating the trenches for the exterior wall footings we put
    down a “mud slab”— basically a thin coating of concrete over the
    earth which could then be trowelled level. That gave us a nice flat
    surface to lay our insulation down on. We then put down 4” of high
    density expanded polyethylene (EPS) foam.The concrete is then poured
    over that.

    The sides of the outside wall footings will be insulated with 4” EPS
    as well. You can see the white EPS on the interior face of the
    footings. It does double duty as a form for the concrete. On the
    exterior side of the footings you see the insulation is a different
    color. This insulation board is used as a form for the footing and
    will be removed. Why? Because we are waterproofing the exterior walls
    right down to the sides of the footings. Once the concrete walls are
    poured, we will apply the waterproofing membrane, then come back and
    insulate the entire wall and sides of footings with the EPS foam. The other two footing photos show the footing for a pier inside the house before and after the concrete is poured.

  • Site is cleared and footings are in.

    Posted from: MD, USA

    There were two big developments last week. We cleared the site, and we received our building permit.

    This week is off to a fast start.  Footings are already poured, and forms go up tomorrow for concrete foundation walls.

    But before getting into the construction issues, a note about how we chose this particular site. I would like to say that our decision was based solely on Passive House planning principles.  The real world, however, is messier than that. The beauty of the Passive House approach is that it is designed to handle real world situations—even sites that don’t have ideal solar orientation. That’s another reason it works so well for the designer.

    When we decided to undertake the project, Brendan (O’Neill) had already purchased this site for future development.  It made sense to use it and to fit our house to it. The neighborhood is undergoing the usual transition that close-in 1930’s neighborhoods in most growing major cities face. The increasing land values make it unfeasible from a real estate payback standpoint to retrofit and renovate the existing smaller houses.  Once the original owners are gone, these houses often become rental properties, held until the increasing land value makes it profitable to sell for the value of the site alone. With no owner incentive to maintain them, they deteriorate.  When they are finally torn down to make way for larger houses, they are usually in pretty rough condition.

    This was the case with our property.  A small 1930’s cottage was financially unfeasible to renovate. Several houses on the street have already been replaced. On this site we decided that if we were going to replace the existing house with a Passive House, we would do two things:

    1.       Keep as much of the house as possible out of landfills, and

    2.       Try to build more or less on the footprint of the existing house.

    On the first point, we contracted with Second Chance http://secondchanceinc.org, a non-profit that goes through homes slated for demolition removing all items that can be resold—cabinets, appliances, fixtures, doors, hardware, etc. We then contracted with Roll Off Express http://rolloffexpress.com in Finksburg, MD to salvage all materials possible.  ROE set up dumpsters on the site where all demolished materials were placed. They were then taken their facility in Finksburg for sorting and distribution to the appropriate recycling streams.  We will be given an accounting of quantities of materials recycled within a few days.

    Below are pictures of a typical existing house in the neighborhood and a typical new house in the neighborhod.

    More on the footings and foundation in a later post…

  • First Passive House in DC Region now underway.

    Today site clearing begins for the first Passive House in the DC area! Read our press release below…

    Alexandria, VA (August 16, 2010) – On August 16, in a quiet residential neighborhood in Bethesda, MD, site preparation work will begin on the area’s first Passive House, a building standard that is the only affordable way to seriously institute building practices that address climate change. The project is a joint venture between O’Neill Construction Corporation, of Gaithersburg, MD, and Peabody Architects of Alexandria, VA.

     

    Consumes Ninety Percent Less Energy

    Passive House (from the German Passivhaus), now taking hold in the United States, is a leading green-building standard in Europe and the most stringent energy certification standard in the world. It produces buildings that use one-tenth of the heating and cooling energy of conventional buildings, while adding, on average, only 10 to 15 percent to the cost of construction. In larger building types, such as schools and office buildings, this standard is easier to reach and the cost differential versus a conventional building runs even lower. With a new energy bill going up before the Senate this summer, the time could not be more auspicious for the arrival of the Passive House in Washington, DC.

     

    The Passive House approach produces buildings that need so little energy it makes irrelevant the more glamorous and expensive high tech solutions – photovoltaics and geothermal heat pumps – that get most of the attention in terms of tax incentives. It is accomplished with the most prosaic and affordable of materials: lots of insulation and sealants. What makes it all work are highly sophisticated energy modeling software and an assiduous approach to eliminating thermal bridging (the rapid transfer of interior heat to a cool area) in the building envelope —all developed by the Passivhaus Institut in Darmstadt, Germany. Studies conducted on the thousands of European projects completed over the last 15 years have uncovered an additional advantage to this construction approach: very high levels of interior air quality and extremely high ratings for comfort.

     

    Efficient, Attractive, Affordable Home

    The O’Neill-Peabody project, designed in the Craftsman vernacular of the American Foursquare, is out to demonstrate that this exotic sounding European import can look and feel like a traditional American home that sells at a competitive price. Brendan O’Neill Sr., whose firm has built its reputation by recreating traditional building styles, was interested when David Peabody told him about the advantages of Passive House construction, but knew that his customers would not get excited about a building that looked like a box. O’Neill and his son visited two recently completed Passive Houses in Illinois—as it turned out, right in the middle of a true Midwestern blizzard.

     

    “It was as toasty and comfortable as any house I’d ever been in. I looked in the mechanical room and the little heat pump was barely even running. I turned to Brendan, Jr. and said, ‘We’ve got to build one of these.’”  Brendan O’Neill

     

    The project will be completed in spring of 2011.

     

    For more information on this project, the team, and the Passive House program:

    http://www.passivehouse.greenhaus.org

    http://www.passivehouse.us/passiveHouse/PHIUSHome.html

    http://www.passiv.de/index_14PHT.html

     

  • The New American Foursquare

    Passive House – Earth Day News 

    foursquare South Elevation

    Today is Earth Day, and it seems an auspicious time to announce a groundbreaking event… in both senses of that word. On May 24 our first Passive House, and the first Passive House in the DC metro area will begin to take shape on North Chelsea Lane in Bethesda, Maryland. Twelve years ago our firm began the transition toward sustainable design. It has been quite an adventure, and with the construction of this home, we will finally have reached our goal.

    We are calling the project The New American Foursquare. Our goal for this first house is to demonstrate that Passive House construction can be mainstream construction, both in terms of cost and design. On the cost side, the house will cost roughly $225 per square foot, exclusive of land costs – which places it squarely in middle range of high quality custom homes. With regard to design, our influence is the original American Foursquare, developed a hundred years ago by Sears Roebuck as the new house for a growing middle class. You have seen them up and down the Main Streets and Elm Streets of most every American town and city. They were designed to be economical to build and efficient with regard to space. These same principles make them well-suited for Passive House construction.

    Our first project, the first Passive House in the DC metro area.